Article
Building a commercial build-out budget that holds
The budget that gets a tenant in trouble is almost never the construction number. It is the number that was never written down: the permit fees, the design revisions, the furniture, the data cabling, the two weeks of rent paid before the doors opened. We have sat in a lot of closeout meetings where the contract came in as priced and the owner still felt over budget. This is how to build a budget that does not do that.
Write down the whole project, not the contract
Hard costs are what the contractor builds: demolition, framing, mechanical, electrical, plumbing, finishes. Soft costs are the fees around it: architect, engineer, permit, inspections, utility connections, testing and any consultants the use requires. Then there is a third column that gets skipped: furniture, fixtures, equipment, signage, security, audio-visual and network cabling. Put all three columns on the same page from the first draft. A budget that shows only the first column is a partial picture that will surprise you later.
Price from a scope, not a rule of thumb
A per-square-foot figure from a friend's project is a starting point for a conversation, not a budget. Two suites the same size can be a coat of paint apart or a full set of restrooms apart. As soon as you have a floor plan and a finish level, get it priced from that plan. If you do not have drawings yet, write a one-page program: room count, plumbing fixture count, ceiling height, finish level, any equipment. We can price a planning range from that page, labeled as a range that varies by scope and year, and tighten it as the drawings develop.
Look at the shell before you trust it
An existing space carries assumptions: that the electrical service is big enough, that the rooftop unit works, that the restrooms meet current accessibility code, that the slab has no surprises under it. We walk the shell with the drawings, open the ceiling, and check the panel schedule before we commit to a number. Many of the overruns we have seen on build-outs came from a shell that was less ready than the lease described.
Contingency is a line, not an apology
Carry a contingency and treat it as part of the plan. Something will move: a concealed condition, a code comment, a material that goes on backorder, an owner decision that changes mid-build. A reserve lets you handle it without stopping the job. Spend it deliberately and track it. A budget with no contingency is not more accurate. It is just more likely to be exceeded.
Tie the money to the calendar
Know when the draws come due and what milestone each one is tied to. Know the date rent starts and the date the business needs to open, and put them on the same schedule as the construction milestones. Long-lead items, storefront glass, custom millwork, mechanical equipment, get ordered and paid for early, and the cash plan needs to allow for that.
Fixture delivery, furniture install, cabling, signage, final cleaning and the punch list all pile into the end. That is where an unplanned FF&E scope turns into overtime. Our own crews handle receiving, staging and installation of FF&E, so those items are on our schedule and in our budget conversation from the start, instead of arriving as a separate problem the week before opening.
A plan or a program, the lease work letter, the shell condition, your finish standard and your opening date. From those we will build the three columns, the contingency and the schedule, and hand it back as one document you can take to a lender or a partner.
A principal of the company prices the job and then runs it from the site, so the number and the person are the same. Send the plans and the lease, and we will build a budget around the day you open.
Browse everything we build →
