Renovating through hurricane season on the Texas Gulf Coast

Renovating through hurricane season on the Texas Gulf Coast photo. Recommended 1600x900.

A hotel general manager called us two summers ago because a renovation on the property next door lost its scaffolding and a stack of exterior material in one afternoon storm. A renovation that closes its exterior scope before the season does not have that problem, because the work left inside the walls does not care what the sky is doing. That difference comes from a schedule built around the Gulf Coast calendar, not from luck.

Finishing the outside scope before the season peaks

Storm season on the Gulf Coast runs June through November, and the heaviest stretch falls from the middle of August into October. A renovation that includes exterior scope, new glazing, a storefront replacement or refresh work under our Roofing & Exterior Refresh trade, gets that scope scheduled to close up before the heavy stretch begins, whenever the calendar allows it. Because our own glaziers and our exterior refresh crew carry that scope directly, we are not waiting on outside subcontractors to find a window in their July calendars. When exterior work has to run through the peak, we break it into short stages, each one closed up and secure before the crew moves to the next section, with tarps, bracing and pumps staged on site the entire time.

A storm elsewhere still reaches your job

A hurricane that makes landfall three hundred miles away still pulls material off the shelves at every supplier on the coast, pulls crews toward the recovery work, and backs up the inspector's calendar for weeks. Roofing material, glazing and generators are usually the first things to disappear, and what is left afterward costs more. We line up exterior material before the season starts whenever the schedule allows it, and because we run our own glazing and exterior crews instead of leasing them from someone else's calendar, a shortage after a storm slows our renovations less than it slows a job waiting on a subcontractor to become available again.

What happens the week a storm gets a name

Every renovation we run on the coast has a storm plan written before the first day of work, and our superintendent carries it out the moment a storm is named. Loose material and equipment staged for install move into a secured interior room. Dumpsters get emptied and hauled off site. Any wall or opening that is mid-renovation gets covered and braced rather than left exposed. We photograph every room before the crew leaves for their own families, then walk the same rooms with the same photos once the storm has passed, so any damage is documented against a known baseline.

The paperwork that turns a claim into a check

A client's builder's risk policy deserves a close read before the season starts, not after a storm hits: what it covers for a named windstorm, for flood water, for rain driven through an opening, and whether material kept inside the building is treated differently than material staged in a trailer outside it. The deductible matters too. Our daily logs and pre-storm photos are exactly what an adjuster asks for, and having them ready is the difference between a paid claim and a dispute. Any requirements a lender has get written down during pre-construction, before they become a surprise later.

Weather days that are actually built into the plan

A Gulf Coast renovation schedule with nothing set aside for August and September is not a real schedule. We add weather days for the peak weeks and show the client exactly where they sit in the calendar. A quiet season means the job finishes ahead of plan. An active one means the reopening date still holds, because those days were already accounted for. Our project manager calls with an updated plan the moment a forecast changes, before the client has to ask what it means for the job.

We renovate hotels, apartment communities, stores and offices along the Gulf Coast with storm season built into the schedule from day one and the reopening date treated as fixed. Send your plans and the date you want to start, and we will show you exactly where the exterior scope falls on the calendar.

Email Facebook X LinkedIn

Browse everything we build →

Start your project

← All articles

Start your project